Charbonneau Stormwater Improvements Phase 2a
PROJECT DESCRIPTION
The goal of the project is to replace and/or relocate an aging 815-foot section of 12” storm sewer between the Red Course Hole #1 and the adjacent homes and Activity Center to the north, which was installed in the mid-70’s. The current condition of these pipes is in poor condition and are at risk of collapse and/plugging during large rain events. The project team will coordinate with the adjacent community amenities and property owners to plan for as minimal disruption as practical during construction.
STAFF CONTACTS
Staff can be reached via telephone at 503-570-1546.
Ethan Rogers, Civil Engineer
Status Updates
Project Timeline:
- Q1 – Q3 2026: Project fieldwork/data collection, and engineering design/permitting
- Q4 2026: Construction
- Q1 2027: Completion